Reading: Energy delays push Oracle to hedge payments on its Stargate campus
Share
Font ResizerAa
TechflierTechflier
Font ResizerAa
  • Home
  • News
  • Features
  • Spotlight
  • About
  • Newsletter
  • Shop
Search
  • Home
  • News
  • Features
  • Spotlight
  • About
    • Mission
    • Services
    • Contact
  • Newsletter
  • Shop
    • All Items
    • By Category
    • Cart
Have an existing account? Sign In
Follow US
© 2025 Techflier. All Rights Reserved.
News

Energy delays push Oracle to hedge payments on its Stargate campus

Oracle has sent a force majeure notice on Project Jupiter in New Mexico, a step that would let it delay payments if the campus misses its 2028 target.

Techflier Staff
Last updated: September 26, 2026 2:03 am
Techflier
Share
SHARE

Oracle has issued a force majeure notice tied to Project Jupiter, the Stargate data center campus it is building in New Mexico, according to Bloomberg, a step that would let the company withhold payments if the site misses its 2028 opening.

The filing does not mean Oracle wants out. It plans to remain the campus’s anchor tenant, and the notice only buys breathing room on the payment schedule should construction drag. According to Bloomberg, the recipient was a unit of Blue Owl Capital. Energy and commodity contracts treat this as boilerplate, giving a party room to pause its obligations when forces outside its control intervene.

Both sides pushed back on the read-through. Oracle describes Project Jupiter as on schedule and says it is fully committed to New Mexico. Blue Owl says the notice leaves the financial commitments to the multi-year project untouched. Oracle shares still fell about 5%.

Bloom Energy fuel cells burning gas are meant to power the 2.45-gigawatt campus, so a steady fuel supply sits at the heart of the construction timetable. Energy Transfer’s pipeline to the site has slipped close to half a year, with February 1, 2027 now the target, after permit applications were turned down by regulators more than once. A separate air-quality permit still needs a ruling by November 23.

Stargate, the AI buildout that Oracle, OpenAI and SoftBank unveiled alongside President Donald Trump, numbers Project Jupiter among its flagship sites, and the project has turned into a political battleground as the midterms approach.

Jailbreak hunter Alice banks $140M as agent risks climb
Orbital AI Compute: What Google and SpaceX’s Data Center Talks Mean for Startup Infrastructure
Ex-Apptio founders land $21M seed for enterprise AI venture Thira
Isomorphic Labs chases a $50B valuation for AI drug discovery
Syntetica raises $30M backed by Lululemon for nylon recycling
TAGGED:AI infrastructuredata centresNew MexicoOracleProject JupiterStargate
SOURCES:TechCrunchSiliconANGLETech Startups
Share This Article
Facebook Copy Link Print
Previous Article Anthropic commits $11.6B to Akamai for seven years of compute
Next Article Solar maker Avaada Electro courts investors for a $793M debut

Get Some Gear

 

 

 

 

Quick Links

  • News
  • Features
  • Spotlight
  • Newsletter
  • Store

About Techflier

  • About Techflier
  • Services
  • Contact Us
  • Privacy
  • Legal

Indices

TechflierTechflier
Follow US
© 2026 Techflier. All Rights Reserved.
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?